Turnkey works within the scope of the project: 455,000 m³ of excavation, 415,000 m³ of fill, 3,800 meters of curb works, 17,716 m³ of box culvert works, 15,000 m³ of reinforced concrete wall works, 40,000 meters of bored pile works, 10,000 tons of plant-mix works, 25,000 m² of hot-mix asphalt road works, and 4,383 m³ of reinforced concrete bridge works